BWX Technologies has been selected to deploy its BWXT Advanced Nuclear Reactor, or BANR, at Fort Campbell, Kentucky, under the Army’s Janus program. The high-temperature, gas-cooled reactor is intended to provide a dedicated source of electricity and thermal energy at the installation, which sits along the Kentucky-Tennessee border. The selection was announced Aug. 26 as part of a broader Army decision involving five nuclear vendors and five military locations.
The planned Fort Campbell unit will produce 20 megawatts of electricity and 75 megawatts of thermal power. BWXT says one reactor can fit on less than five acres, operate for about four years between refueling cycles and support either combined heat and power or electricity-only generation. Its fuel uses TRISO particles, in which uranium is surrounded by multiple protective layers. The Army says the reactors are meant to strengthen installation resilience while remaining connected to existing utility grids rather than replacing them entirely.
The Janus program provides up to $2.2 billion across fiscal years 2027 through 2031 for the five selected vendors. Payments will be tied to technical milestones, and the prototype reactors will be owned and operated by their contractors. The other pairings are Antares Nuclear with Fort Bragg, General Atomics with Fort Hood, Radiant Industries with Fort Benning and Westinghouse Government Services with Fort Drum. The Army expects private investment alongside federal funding and says the initiative could ultimately support more than 20 microreactors across military installations.
BWXT’s project remains several steps from operation. Its initial work includes final site selection within Fort Campbell, Army regulatory processes, TRISO fuel fabrication at existing facilities, site characterization, supply-chain preparation and creation of an operating structure. Construction is targeted to begin in late 2028, with reactor operations expected in the early 2030s. That schedule differs from the Army’s separate goal of having a first Army-regulated reactor operating at a domestic military installation by September 2028.
The Fort Campbell award adds an advanced-reactor project to an established nuclear manufacturing business. BWXT has also signed a nonbinding letter of intent with Tata Chemicals to explore as many as eight BANR units in Wyoming, leaving that potential expansion separate from the Army award.